Irkutsk Aviation Plant Streamlines Production Processes to Increase MC-21 Output

mc 21 fuselage panels
Manufacture and handling of MC-21 fuselage panels at the aircraft's final assembly plant / Photo © Aviation of Russia

Irkutsk Aviation Plant (IAZ), part of Yakovlev, is targeting a reduction in the MC-21 final assembly cycle from 40 to 10 calendar days as it prepares to increase production of the Russian narrowbody airliner. The target rate of 36 aircraft a year will require improvements not only on the assembly line but also across production support functions and the aircraft’s supply chain.

The factory has largely completed its main programme of production equipment upgrades, shifting the focus towards operational efficiency. Management is now concentrating on removing bottlenecks in production planning, technical documentation approval, component deliveries and the preparation of workstations. Delays in these areas can constrain output even when assembly capacity and labour are available.

One example of the changes involves the approval process for installing cabin lighting. Under the previous procedure, the relevant production documentation required 1,661 signatures, including those of shop-floor workers. A lean-manufacturing initiative reduced this number to 41, cutting the administrative burden without changing the installation process itself. IAZ is applying the same approach to other procedures that add time and cost without contributing to the aircraft’s production value.

The plant has established working groups to identify and eliminate such inefficiencies across different levels of management. Their remit covers both manufacturing operations and the business processes supporting them. The initiative is intended to become a permanent part of production management as output increases, when even relatively minor delays can disrupt the assembly schedule.

Supply-chain performance will be a major factor in achieving the production targets. IAZ’s ability to increase assembly rates will depend on whether suppliers can deliver components at the required frequency and volume. Improving the performance of the final assembly line alone will not produce the intended results if upstream manufacturing and logistics cannot maintain the same production rhythm.

IAZ’s production ramp-up is scheduled to proceed in stages. The plant is targeting one aircraft every two months in 2027, followed by annual output of 12-15 aircraft, then 24, with a longer-term objective of 36 aircraft a year. Reducing the assembly cycle to 10 days is intended to support the final stage of this expansion.

The factory has completed two production-standard MC-21-310 aircraft. The first, manufacturer’s serial number MS.0014 (registration 73362), made its maiden flight on 3 August 2026. The second, MS.0015, flew on 23 November. According to IAZ General Director Andrei Soynov, the plant will complete cabin installation and painting for all MC-21 aircraft before handing them over to customers at Irkutsk.

The production ramp-up is underpinned by a substantial order backlog. Aeroflot has contracted for an additional 90 MC-21-310s, with a further agreement for 92 aircraft under preparation. If concluded, these commitments would bring the airline’s total order book to 200 aircraft, providing IAZ with a substantial workload for the coming decade.

Aeroflot expects to receive its first eight aircraft after approval of the MC-21’s major design changes, with type certification targeted for approximately one year from the time of the source interview. The pace of deliveries will therefore depend on both certification progress and IAZ’s ability to increase production capacity in line with the contracted demand.